Access was through a farmyard and down a stone track, then it got interesting…
- 30° slope
Off the farm track, access was up an uneven grassed slope of around degrees, 1,500kg was right on the limit of the machine’s capacity.
- A washed out culvert
Right at the top of the incline there was a washed out culvert.
- Limited space in the compound
Once in the compound, there was limited space to work.
All challenges were identified at the survey and taken into account in the quote and the Safe System of Work. The customer knew what had to happen before delivery day, and what it would take.
Our Solutions
Our custom TC2500 Pro with ramps, timbers, and a lifting gantry
We knew it was going to be a challenge because the incline leading to the compound was right on the limit of what the carrier could take with a 1,250kg payload, especially as the generator was top heavy, and partly fuelled.
On the day:
- We had arranged to meet the generator in the farmyard to have it loaded onto the Tracked Carrier
- The Tracked Carrier took the generator up the slope and across rated ramps we’d set up to bridge the culvert
- A 3t lifting gantry was taken up on one of our 4×4 dropside vans and set up in the compound
- The Tracked Carrier positioned the generator beneath the gantry and above its concrete plinth
- The gantry then took the weight allowing the Tracked Carrier to move, and the generator was lowered to its destination
The Final Result
The result. Up the hill, across the culvery and in the compound, right first time
This delivery succeeded because:
- We surveyed in advance
- We have the right equipment, and just as importantly, we know our equipment’s capabilities
- We planned the job properly
Attention to detail like this is what keeps our Right First Time rate at 99.9%.
FAQs
Yes, every job. Desktop review of drawings and photos first, then a site survey where one is needed. Once we’ve surveyed a site, we take liability for the delivery.
We flag it in the survey and have it certified before the job. Nothing is lifted from an uncertified beam.
Yes. Where there’s no crane access, UK Teleport uses powered stair climbers to move cabinets up stairwells, then a chain hoist rigged from a certified beam to lift them through the roof hatch into the plant room.