Back-up generator delivery

Partly fuelled back-up generator weighing 1,250kg delivered to a compound up a steep hill. No access for a crane, no problem for our tracked carrier.

Project Overview

The Challenges

Access was through a farmyard and down a stone track, then it got interesting…

  1. 30° slope

Off the farm track, access was up an uneven grassed slope of around degrees, 1,500kg was right on the limit of the machine’s capacity.

  1. A washed out culvert

Right at the top of the incline there was a washed out culvert.

  1. Limited space in the compound

Once in the compound, there was limited space to work.

All challenges were identified at the survey and taken into account in the quote and the Safe System of Work. The customer knew what had to happen before delivery day, and what it would take.

Our Solutions

Our custom TC2500 Pro with ramps, timbers, and a lifting gantry

We knew it was going to be a challenge because the incline leading to the compound was right on the limit of what the carrier could take with a 1,250kg payload, especially as the generator was top heavy, and partly fuelled.

On the day:

  • We had arranged to meet the generator in the farmyard to have it loaded onto the Tracked Carrier
  • The Tracked Carrier took the generator up the slope and across rated ramps we’d set up to bridge the culvert
  • A 3t lifting gantry was taken up on one of our 4×4 dropside vans and set up in the compound
  • The Tracked Carrier positioned the generator beneath the gantry and above its concrete plinth
  • The gantry then took the weight allowing the Tracked Carrier to move, and the generator was lowered to its destination

The Final Result

The result. Up the hill, across the culvery and in the compound, right first time

This delivery succeeded because:

  • We surveyed in advance
  • We have the right equipment, and just as importantly, we know our equipment’s capabilities
  • We planned the job properly

Attention to detail like this is what keeps our Right First Time rate at 99.9%.

Got a cabinet that won’t fit in the lift? Let’s talk.

FAQs

Do you survey before you quote?

Yes, every job. Desktop review of drawings and photos first, then a site survey where one is needed. Once we’ve surveyed a site, we take liability for the delivery.

What happens if the lifting beam on site isn’t certified?

We flag it in the survey and have it certified before the job. Nothing is lifted from an uncertified beam.

Can you deliver a telecoms cabinet to a rooftop without a crane?

Yes. Where there’s no crane access, UK Teleport uses powered stair climbers to move cabinets up stairwells, then a chain hoist rigged from a certified beam to lift them through the roof hatch into the plant room.

Go to Top